Productivity Enhancement of Plastic Manufacturing "El Ameen Factory"

Supervisor(s):

Dr. L. Gaafar

Dr. M. Younan


Team Members:

Ahmed Sayed Salama

Hanady Mohamed Hussein

Heba Ibrahim Saleh

Karim Ashraf Hussein

Menattallah Farag

Mohamed Hussein Said

Objectives:

bullet

Reduce the time of the changeover process.

bullet

Find an alternative welding technique to weld the tank insert to the flush box after changing its material from polystyrene to polypropylene.

Achievements:

bullet

The changeover procedure was reduced by about 50%, a modified changeover process was formed and workers were trained to follow it.

bullet

Alternative welding techniques were experimented and hot plate welding proved to be the best alternative weld strength of 118.6% of the parent material.

 